Preliminary project report for a road project must contain___________________?
A. The detailed estimated cost based on detailed design
B. The several alternatives of the project that have been considered
C. The soil survey, traffic survey, concept design and approximate cost
D. The contract documents for inviting tenders
The most suitable type of equipment for compaction of cohesive soils is_________________?
A. Smooth-wheeled rollers
B. Vibratory rollers
C. Sheep foot rollers
D. Tampers
Grader is used mainly for___________________?
A. Trimming and finishing
B. Shaping and trimming
C. Finishing and shaping
D. Finishing, shaping and trimming
The correct sequence of these activities is________________?
ConSider the following activities in a building construction?
D. None of these
Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
A. On commencement of work at site for payment of loan taken by him
B. For the purchase of construction materials
C. For the payment of advances to labour and other staff
D. For all activities required to start the work at site on finalization of the contract document
In time-cost optimization of a project, crashing is done____________?
A. On all the activities
B. On all the activities lying on the critical path
C. Only on activities lying on the orginal critical path and having flatter cost slopes
D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope