In the critical path method of construction planning, Free Float can be_____________?
A. Consider the following statements ?
B. 1. greater than total float.
C. 2. greater than independent float
D. 3. equal to total float.
The time corresponding to minimum total project cost is_______________?
A. Crash time
B. Normal time
C. Optimistic time
D. Between normal time and crash time
During the construction period, price variation clause in contracts caters to__________________?
A. Increase in rates of only important materials
B. Variation in cost in materials element, labour element and petrol-oil-lubricant element
C. Variation in total cost of the project on an ad hoc basis
D. Rate of inflation
Sinking fund is_______________?
A. The fund for rebuilding a structure when its economic life is over
B. Raised to meet maintenance costs
C. The total sum to be paid to the municipal authorities by the tenants
D. A part of the money kept in reserve for providing additional structures and structural modifications
In resources levelling________________?
A. Total duration of project is reduced
B. Total duration of project is increased
C. Uniform demand of resources is achieved
D. Cost of project is controlled