Q
During the construction period, price variation clause in contracts caters to__________________?
-
A
A. Increase in rates of only important materials
-
B
B. Variation in cost in materials element, labour element and petrol-oil-lubricant element
-
C
C. Variation in total cost of the project on an ad hoc basis
-
D
D. Rate of inflation
Correct Answer:
B. B. Variation in cost in materials element, labour element and petrol-oil-lubricant element