Q
Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
-
A
A. On commencement of work at site for payment of loan taken by him
-
B
B. For the purchase of construction materials
-
C
C. For the payment of advances to labour and other staff
-
D
D. For all activities required to start the work at site on finalization of the contract document
Correct Answer:
D. D. For all activities required to start the work at site on finalization of the contract document