Q
In time-cost optimization of a project, crashing is done____________?
-
A
A. On all the activities
-
B
B. On all the activities lying on the critical path
-
C
C. Only on activities lying on the orginal critical path and having flatter cost slopes
-
D
D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Correct Answer:
D. D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope