Q In time-cost optimization of a project, crashing is done____________?
  • A A. On all the activities
  • B B. On all the activities lying on the critical path
  • C C. Only on activities lying on the orginal critical path and having flatter cost slopes
  • D D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope