When an activity is called a critical activity?
A. When earliest start time (est) is equal to the earliest finish time (eft)
B. When earliest start time (est) plus the time taken by it is equal to the latest finish time (lft)
C. When latest start time (lst) plus the time taken by it is equal to the latest finish time(lft)
D. When earliest start time (est) plus the time taken by it is equal to the earliest finish time (eft)
Among the following, pick the option that can be an example of an activity.
A. Start the motor
B. Loan approved
C. Refund successful
D. Arrange foreign exchange
Which of the following can be an example of an event?
A. Start the motor
B. Install machinery
C. Refund money
D. Arrange foreign exchange
What is a critical activity?
A. A specific instant of time which marks the start and the end of an activity
B. It is an element of the project and has a specific time duration
C. It is a dotted line connecting the two head events and consumes no time
D. An activity which if consumes more time than the estimated time that results in the delay of the entire project