Q From the given below statements, find the incorrect statement. i. A critical path has zero float. ii. A critical path has both critical and non-critical activities. iii. A critical path is the longest path and consumes maximum time and resources.
  • A A. I only
  • B B. Ii only
  • C C. I and iii only
  • D D. Iii only