When an activity is called a critical activity?
A. When earliest start time (est) is equal to the earliest finish time (eft)
B. When earliest start time (est) plus the time taken by it is equal to the latest finish time (lft)
C. When latest start time (lst) plus the time taken by it is equal to the latest finish time(lft)
D. When earliest start time (est) plus the time taken by it is equal to the earliest finish time (eft)
What is also called an arrow diagram?
A. Activity diagram
B. Project diagram
C. Network diagram
D. Scatter diagram
Match the following. p) AOA i) Activity diagram q) AON ii) Network diagram r) Arrow diagram iii) PERT iv) CPM
A. P €? ii, q €? i, r €? iii
B. P €? ii, q €? i, r €? iv
C. P €? iii, q €? iv, r €? ii
D. P €? i, q €? ii, r €? iii
Match the following. p) Negative float i) Just sufficient resources q) Zero float ii) Surplus resources r) Positive float iii) Inadequate resources
A. P €? ii, q €? i, r €? iii
B. P €? ii, q €? iii, r €? i
C. P €? iii, q €? i, r €? ii