Find the incorrect statement.
A. Event and node are synonyms
B. An event is represented by a circle
C. An activity is shown by a square
D. A dummy activity is critical when its earliest start time (est) and latest finish time (lft) are the same
Which of the following can be an example of an event?
A. Start the motor
B. Install machinery
C. Refund money
D. Arrange foreign exchange
Among the following, pick the option that can be an example of an activity.
A. Start the motor
B. Loan approved
C. Refund successful
D. Arrange foreign exchange