Q What is a critical activity?
  • A A. A specific instant of time which marks the start and the end of an activity
  • B B. It is an element of the project and has a specific time duration
  • C C. It is a dotted line connecting the two head events and consumes no time
  • D D. An activity which if consumes more time than the estimated time that results in the delay of the entire project