Which of the following can be an example of an event?
  • A. Start the motor
  • B. Install machinery
  • C. Refund money
  • D. Arrange foreign exchange
Among the following, pick the option that can be an example of an activity.
  • A. Start the motor
  • B. Loan approved
  • C. Refund successful
  • D. Arrange foreign exchange
Identify a dummy activity in the below-shown network diagram.
  • A. Activity 1
  • B. Activity 6
  • C. Activity 8
  • D. Activity 2
When an activity is called a critical activity?
  • A. When earliest start time (est) is equal to the earliest finish time (eft)
  • B. When earliest start time (est) plus the time taken by it is equal to the latest finish time (lft)
  • C. When latest start time (lst) plus the time taken by it is equal to the latest finish time(lft)
  • D. When earliest start time (est) plus the time taken by it is equal to the earliest finish time (eft)
What is also called an arrow diagram?
  • A. Activity diagram
  • B. Project diagram
  • C. Network diagram
  • D. Scatter diagram