In the bar chart planning____________?
A. Consider the following statements?
B. 1. interdependence of the operations cannot be portrayed
C. 2. progress of work can be measured
D. 3. spare time of the activities can be determined
At a work site, statistical quality control of concrete means________________?
A. Measurement of risks to eliminate failures
B. Applying the theory’ of probability to sample testing or inspection
C. Reduction in wastage of inspection costs
D. Reduction in costs for the removal of defects
In time-cost optimization of a project, crashing is done____________?
A. On all the activities
B. On all the activities lying on the critical path
C. Only on activities lying on the orginal critical path and having flatter cost slopes
D. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
A. On commencement of work at site for payment of loan taken by him
B. For the purchase of construction materials
C. For the payment of advances to labour and other staff
D. For all activities required to start the work at site on finalization of the contract document
The correct sequence of these activities is________________?
ConSider the following activities in a building construction?
D. None of these
Grader is used mainly for___________________?
A. Trimming and finishing
B. Shaping and trimming
C. Finishing and shaping
D. Finishing, shaping and trimming