In the bar chart planning____________?
AA. Consider the following statements?
BB. 1. interdependence of the operations cannot be portrayed
CC. 2. progress of work can be measured
DD. 3. spare time of the activities can be determined
Correct Answer:
1. Interdependence of the operations cannot be portrayed
2. progress of work can be measured
3. spare time of the activities can be determined
4. schedule cannot be updated