A. Latest start time of succeeding event -earliest finish time of preceding event activity time B. Latest start time of the event – earliest start time of the event C. Latest finish time of event – earliest finish time of the event D. Anyone of the above
A. consequential effects of lack in one activity on omer B. consequential effects of lack in one activity on the finish date C. free time available for an activity can’t be predicted D. effective monitoring/controlling can’t be done
A. establishes the relative priorities among various activities on a common basis B. determines the status of each activity C. adjusts automatically changes in activity progress D. is a dynamic system
A. To concentrate his attention on critical activities B. To divert the resources from non-critical advanced activities to critical activities C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project D. All of the above