Mechanical Engineering Mcqs
Q Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
  • A A. Latest start time of succeeding event -earliest finish time of preceding event activity time
  • B B. Latest start time of the event – earliest start time of the event
  • C C. Latest finish time of event – earliest finish time of the event
  • D D. Anyone of the above