Q
Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
-
A
A. Latest start time of succeeding event -earliest finish time of preceding event activity time
-
B
B. Latest start time of the event β earliest start time of the event
-
C
C. Latest finish time of event β earliest finish time of the event
-
D
D. Anyone of the above
Correct Answer:
D. D. Anyone of the above