Q
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?
-
A
A. Consumes time, but no resources
-
B
B. Consumes resources but no time
-
C
C. Consumes neither time nor resources
-
D
D. Is a dangling event
Correct Answer:
C. C. Consumes neither time nor resources