If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?
A. Latest start time – earliest start time
B. Latest finish time – earliest finish time (eft)
C. Tl-eft
D. All of the above
Emergency rush order can be pushed more effectively in__________________?
A. Job production
B. Automatic production
C. Continuous production
D. Intermittent production
The first method invented for planning projects was________________?
A. Bar chart method
B. Milestone chart
C. Critical path method (cpm)
D. Programme evaluation and review technique (pert)
A milestone chart_______________________?
A. shows the inter dependences of various jobs
B. depicts the delay of jobs, if any
C. points outgoing ahead of schedule of jobs, if any
D. all of the above