Industrial Management Network Analysis Set 4
Q Calculate the total float available for an activity if the LST and EST are 12 and 10 minutes respectively.
  • A A. 1 minute
  • B B. 11 minutes
  • C C. 12 minutes
  • D D. 2 minutes