Which of the following may affect the floats of both the succeeding activities as well as preceding activities?
AA. Total float
BB. Free float
CC. Independent float
DD. Free and independent
Correct Answer:
A. A. Total float
Explanation:
Total float is the additional time available for non-critical activities without delaying the project duration. It may affect the floats of both the succeeding activities as well as preceding activities.