Industrial Management Network Analysis Set 4
Q Find the free float of activity if the earliest start time (EST) of the tail event and the head event are 2 and 10 minutes respectively. Consider the activity duration as 4 minutes.
  • A A. 4 minutes
  • B B. 9 minutes
  • C C. 8 minutes
  • D D. 6 minutes