Industrial Management MCQs

33 MCQs  (Page 2 of 4)

Which of the following can be an example of an event?
A. Start the motor
B. Install machinery
C. Refund money
D. Arrange foreign exchange
Among the following, pick the option that can be an example of an activity.
A. Start the motor
B. Loan approved
C. Refund successful
D. Arrange foreign exchange
When an activity is called a critical activity?
A. When earliest start time (est) is equal to the earliest finish time (eft)
B. When earliest start time (est) plus the time taken by it is equal to the latest finish time (lft)
C. When latest start time (lst) plus the time taken by it is equal to the latest finish time(lft)
D. When earliest start time (est) plus the time taken by it is equal to the earliest finish time (eft)
What is also called an arrow diagram?
A. Activity diagram
B. Project diagram
C. Network diagram
D. Scatter diagram
Match the following. p) AOA i) Activity diagram q) AON ii) Network diagram r) Arrow diagram iii) PERT iv) CPM
A. P €? ii, q €? i, r €? iii
B. P €? ii, q €? i, r €? iv
C. P €? iii, q €? iv, r €? ii
D. P €? i, q €? ii, r €? iii