Total float for any activity is defined as the difference between________________?
A. Its latest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest start time and earliest finish time
D. Its earliest finish time and earliest start time for its successor activity
Free float for any activity is defined as the difference between__________________?
A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successor activity
The independent float affects only_______________?
A. Preceding activities
B. Succeeding activities
C. The particular activity involved
D. None of the above
Economic saving of time results by crashing_________________?
A. Cheapest critical activity
B. Cheapest non-critical activity
C. Costliest critical activity
D. Costliest non-critical activity
Slack time refers to_______________?
A. An activity
B. An event
C. Both event and activity
D. None of the above
The constraints in case of resource smoothening operation would be_______________?
A. Resources
B. Project duration time
C. Both resources and project duration time
D. None of the above
Crash project duration is obtained by summing the________________?
A. Normal durations for all the activities
B. Crash durations for all activities
C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities