Civil Engineering MCQs
Q Crash project duration is obtained by summing the________________?
  • A A. Normal durations for all the activities
  • B B. Crash durations for all activities
  • C C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
  • D D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities