Crash project duration is obtained by summing the________________?
AA. Normal durations for all the activities
BB. Crash durations for all activities
CC. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
DD. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Correct Answer:
D. D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities