Q
Economic saving of time results by crashing_________________?
-
A
A. Cheapest critical activity
-
B
B. Cheapest non-critical activity
-
C
C. Costliest critical activity
-
D
D. Costliest non-critical activity
Correct Answer:
A. A. Cheapest critical activity