Interfering float is the difference between__________________?
A. Total float and free float
B. Total float and independent float
C. Free float and independent float
D. None of the above
Updating may result in_________________?
A. Change of critical path
B. Decrease of project completion time
C. Increase of project completion time
D. All of the above
The process of incorporating changes and rescheduling or replanning is called_______________?
A. Resource levelling
B. Resource smoothening
C. Updating
D. Critical path scheduling
The reduction in project time normally results in_______________?
A. Decreasing the direct cost and increasing indirect cost
B. Increasing the direct cost and decreasing the indirect cost
C. Increasing the direct cost and indirect cost both
D. Decreasing the direct cost and indirect cost both
Critical path_____________?
A. Is always longest
B. Is always shortest
C. May be longest
D. May be shortest