The reduction in project time normally results in_______________?
-
A
A. Decreasing the direct cost and increasing indirect cost
-
B
B. Increasing the direct cost and decreasing the indirect cost
-
C
C. Increasing the direct cost and indirect cost both
-
D
D. Decreasing the direct cost and indirect cost both
Correct Answer:
B. B. Increasing the direct cost and decreasing the indirect cost