In Belgium method of tunneling _________________?
A. Construction of side walls is completed before invert and roof arch are built
B. Construction of roof arch is completed before side walls and invert are built
C. Construction of invert is completed before side walls and roof arch are built
D. Construction of invert and side walls is completed before roof arch is built
Which one of the following is considered to be an advantage of the heading and benching method of tunnel construction?
A. It is suitable for construction in unstable rocks
B. In this method, it is easy to install timber support
C. Tunnelling can be continuous and the work can be expedited
D. In case of excessive water, it is easy to take correct steps
What is the correct sequence of the following events in rock tunnelling?
A. 1. marking tunnel profile
B. 2. loading explosives and blasting
C. 3. checking misfire
D. 4. mucking