In Belgium method of tunneling _________________?
-
A
A. Construction of side walls is completed before invert and roof arch are built
-
B
B. Construction of roof arch is completed before side walls and invert are built
-
C
C. Construction of invert is completed before side walls and roof arch are built
-
D
D. Construction of invert and side walls is completed before roof arch is built
Correct Answer:
B. B. Construction of roof arch is completed before side walls and invert are built