Q In Belgium method of tunneling _________________?
  • A A. Construction of side walls is completed before invert and roof arch are built
  • B B. Construction of roof arch is completed before side walls and invert are built
  • C C. Construction of invert is completed before side walls and roof arch are built
  • D D. Construction of invert and side walls is completed before roof arch is built