Deviation from mandatory advertisement is permissible with prior approval of the Authority where:
  • Publication could jeopardize national security, or relates to proprietary/IP information available from a single source
  • The value is below Rs. 3 million
  • The procurement is urgent
  • The PAO certifies it
Pre-qualification under Rule 15 may be engaged in for all of the following EXCEPT:
  • Services
  • Expensive and technically complex equipment
  • Civil works and turnkey projects
  • Standard off-the-shelf stationery
A procuring agency shall communicate to suppliers who have NOT been pre-qualified:
  • Only the names of pre-qualified firms
  • Nothing, as PQ is discretionary
  • The reasons for not pre-qualifying them
  • The scores of other bidders
The maximum duration of a CLOSED framework agreement is:
  • One year
  • Five years
  • Two years
  • Three years
The factor or percentage for price adjustment under framework agreements is approved by the:
  • Grievance Redressal Committee
  • Principal Accounting Officer
  • Finance Division
  • PPRA
Under Rule 17, a procuring agency having credible reasons may require information on a supplier's competence:
  • At any stage, whether pre-qualified or not, after recording reasons in writing
  • Only with PPRA approval
  • Only before pre-qualification
  • Only after award
A procuring agency SHALL disqualify a supplier if it finds that the information submitted concerning his qualification was:
  • Not notarized
  • Submitted in English only
  • Submitted late
  • False and materially inaccurate or incomplete
Blacklisting for failure to perform contractual obligations (Rule 19(1)(b)) shall be initiated:
  • Immediately upon breach
  • After exhausting the forum of arbitration, where such provision exists in the contract
  • After one year of breach
  • Only with the approval of PPRA