The critical path of a network represents_______________________?
A. The minimum time required for completion of project
B. The maximum time required for completion of project
C. Maximum cost required for completion of project
D. Minimum cost required for completion of project
The critical activity has____________________?
A. Maximum float
B. Minimum float
C. Zero float,
D. Average float
Pick up the correct statement about relationship between various floats______________________?
A. free float = total float
B. independent float = total float
C. independent float > free float