Q
Which of the following is associated with slack?
AA. An event
BB. An activity
CC. A network diagram
DD. A critical path
Correct Answer:
A. A. An event
Explanation:
Slack is for an event and float is for an activity. In general, both can be interchangeable. A critical path always has zero float. Whether it is float or slack, it indicates that extra time is available for the non-critical activities without delaying the project duration with the given resources.