Q
Latest start of an activity is always________________?
-
A
A. Greater than or equal to latest event time of preceding node
-
B
B. Less than or equal to latest event time of preceding node
-
C
C. Equal to latest event time of preceding node
-
D
D. Less than latest event time of preceding node
Correct Answer:
A. A. Greater than or equal to latest event time of preceding node