If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then______________?
AA. Expected time of activity a is greater than the expected time of activity b
BB. Expected time of activity b is greater than the expected time of activity a
CC. Expected time of both activities a and b are same
DD. None of the above
Correct Answer:
C. C. Expected time of both activities a and b are same