In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
-
A
A. Normal distribution curve
-
B
B. Posison’s distribution curve
-
C
C. Beta – distribution curve
-
D
D. None of the above
Correct Answer:
C. C. Beta – distribution curve