Q
Earliest finish of an activity is always_______________?
-
A
A. Greater than earliest event time of the following node
-
B
B. Less than earliest event time of the following node
-
C
C. Less than or equal to earliest event time of the following node
-
D
D. Greater than or equal to earliest event time of the following node
Correct Answer:
C. C. Less than or equal to earliest event time of the following node