Question 1
A blacklisted bidder engaged in an ongoing public contract:
FIA Superintedent Model Paper 2026
Question 2
A bidder blacklisted by a foreign country or international organization shall be:
FIA Superintedent Model Paper 2026
Question 3
The principal method of procurement of goods, services and works under the PP Rules is:
FIA Superintedent Model Paper 2026
Question 4
Open competitive bidding is required if the cost of the object is more than:
FIA Superintedent Model Paper 2026
Question 5
For import of commodities to meet demand-supply gap under Rule 21A, the bidding procedure to be adopted is:
FIA Superintedent Model Paper 2026
Question 6
Bid security, where required, shall not exceed ______ of the estimated value of procurement.
FIA Superintedent Model Paper 2026
Question 7
Where the procuring agency does not require bid security, the bidder shall submit:
FIA Superintedent Model Paper 2026
Question 8
An extension of bid validity, where necessary, shall be for not more than:
FIA Superintedent Model Paper 2026
Question 9
Bidders who do NOT agree to extension of bid validity shall be:
FIA Superintedent Model Paper 2026
Question 10
Extension of time for submission of bids shall be done after recording reasons and advertised: