Network Analysis Set 3 — Test 1
Page 1 of 1
Question 1
From the given below statements, find the incorrect statement. i. A critical path has zero float. ii. A critical path has both critical and non-critical activities. iii. A critical path is the longest path and consumes maximum time and resources.
PPSC - Past Papers - Most Repeated
Question 2
When an activity is called a critical activity?
PPSC - Past Papers - Most Repeated
Question 3
What is also called an arrow diagram?
PPSC - Past Papers - Most Repeated
Question 4
Match the following. p) AOA i) Activity diagram q) AON ii) Network diagram r) Arrow diagram iii) PERT iv) CPM
PPSC - Past Papers - Most Repeated
Question 5
Calculate the earliest start time (EST) for an activity ‘A’ if the duration of the activity is 3 minutes and the earliest finish time (EFT) is 14 minutes.
PPSC - Past Papers - Most Repeated
Question 6
Find the latest finish time (LFT) when the latest start time (LST) and duration of the activity are 6 minutes and 4 minutes respectively.
PPSC - Past Papers - Most Repeated
Question 7
Match the following. p) Negative float i) Just sufficient resources q) Zero float ii) Surplus resources r) Positive float iii) Inadequate resources
PPSC - Past Papers - Most Repeated