Q Which of the following is not an option to achieve reliable cost and effort estimate ?
  • A A. Base estimates on similar projects that have already been completed
  • B B. Use one or more empirical models for software cost and effort estimation
  • C C. Use relatively simple decomposition techniques to generate project cost and effort estimates
  • D D. The ability to translate the size estimate into human effort, calendar time, and dollars