Where formal signing is required, a procurement contract comes into force from:
-
A
The date both procuring agency and successful bidder affix signatures
-
B
The date of announcement of evaluation report
-
C
The date of performance guarantee submission
-
D
The date of notice of acceptance
Correct Answer:
A. The date both procuring agency and successful bidder affix signatures
Explanation:
Rule 44(b); without formal signing → from notice of acceptance/PO (44(a)); conditional contracts → on fulfilment.