Q
Under Rule 40, negotiations with the successful bidder are permitted on all of the following EXCEPT:
-
A
Special conditions of the contract
-
B
Methodology
-
C
Reduction in the cost of the contract
-
D
Work plan and staffing
Correct Answer:
C. Reduction in the cost of the contract
Explanation:
Rule 40(1): without changing cost and scope.