Q The institute of Electronics and Communications Engineers of the Philippines (IECEP) is planning to put up its own building. Two proposals being considered are below.
  • A 1. The construction of the building now to cost p 400,000
  • B 2. The construction of a smaller building now to cost p300,000 and at the end of 5 years, an extension to be added to cost p 200,000.
  • C By How much is proposal b more economical than proposal a if interest rate is 20% and depreciation to be neglected ?