Q
The difference between actual quantity use and input quantity for output is multiplied with budgeted price to calculate ___________?
-
A
A. Efficiency deviation
-
B
B. Efficiency variance
-
C
C. Budgeted variance
-
D
D. Usage variance
Correct Answer:
B. B. Efficiency variance