Q
The costing and allocating situation, in which the indirect cost allocated amount is less than actually incurred amount is known as ___________?
-
A
A. Over allocated budget
-
B
B. Under allocated budget
-
C
C. Under allocated indirect cost
-
D
D. Over allocated direct cost
Correct Answer:
C. C. Under allocated indirect cost