Q
The assumption in PERT is__________________?
-
A
A. A project will always be behind schedule, if left uncorrected
-
B
B. Cost of project will always be more than the estimated cost, if no timely corrections are taken
-
C
C. A project can be subdivided into a set of predictable, independent activities
-
D
D. Activities are fixed and canβt be changed ,
Correct Answer:
C. C. A project can be subdivided into a set of predictable, independent activities