Q
Pick up the correct step used for scheduling a project by C.P.M.__________________?
-
A
A. a project is divided into various activities
-
B
B. required time for each activity is established
-
C
C. sequence of various activities is made according to their importance
-
D
D. network is drawn by connecting the activities and the events