Q Pick up the correct step used for scheduling a project by C.P.M.__________________?
  • A A. a project is divided into various activities
  • B B. required time for each activity is established
  • C C. sequence of various activities is made according to their importance
  • D D. network is drawn by connecting the activities and the events