Q
Negotiated tendering on grounds of extreme urgency is allowed only when the circumstances:
-
A
Arise from delay in budget release
-
B
Involve value below Rs. 3 million
-
C
Are certified by PPRA
-
D
Are unforeseeable and not attributable to the procuring agency
Correct Answer:
D. Are unforeseeable and not attributable to the procuring agency
Explanation:
Rule 42(d)(iii); reasons must be recorded.