Q
In two stage bidding, time allowed for submitting revised bids after changes in requirements shall not be less than:
-
A
7 days for NCB and 15 days for ICB
-
B
15 days for NCB and 30 days for ICB
-
C
30 days for both
-
D
10 days for NCB and 20 days for ICB
Correct Answer:
B. 15 days for NCB and 30 days for ICB
Explanation:
Second proviso to Rule 36(c)(iv).