Q
In “full face” method of constructing tunnels, the first operation relates to______________?
-
A
A. Removal of bottom portion
-
B
B. Excavation of one drift in the centre
-
C
C. Removal of top portion
-
D
D. Excavation being done along the periphery
Correct Answer:
D. D. Excavation being done along the periphery