Civil Engineering MCQs
Q If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?
  • A A. 50%
  • B B. Less than 50%
  • C C. More than 50%
  • D D. 100%