Q If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be__________________?
  • A A. 1 + (0.9)010
  • B B. 1 – (0.9)°l0
  • C C. 1/(1-0.9°10)
  • D D. 1/(1+ 0.9010)